Pilot plant for agitation leaching of the flotation tailings

Autor

Božić, Dragana
Avramović, Ljiljana
Trifunović, Vanja
Marković, Radmila
Stevanović, Zoran
Požega, Emina
Marjanović, Vesna

Opis (eng)

Abstract: The flotation concentration plant in the RTB Bor started working at the industrial scale in 1933 and terminated in 2003. During those seventy years of copper ore processing, the flotation plant had disposed a huge amount of solid waste in the old flotation tailing dump. Chemical analysis had shown that an average concentration of targeted metals in tailings is: 0.23 % Cu, 0.4 g/t Au and 2.0 g/t Ag. The leaching degrees of analyzed elements, achieved after leaching the composite sample of flotation tailings in the pilot plant were: 54.35% Cu, 15.35% Fe, 3.75% Ag and 3.75 % Au.

Jezik

engleski

Datum

2024

Licenca

Creative Commons licenca
Ovo delo je licencirano pod uslovima licence
Creative Commons CC BY 4.0 - Creative Commons Autorstvo 4.0 International License.

http://creativecommons.org/licenses/by/4.0/legalcode

Predmet

Keywords: leaching, flotation tailings, pilot plant.