OPTIMIZACIJA RASPOREDA ZEMLJANIH MASA PRI GRADNJI ŠUMSKIH PUTEVA
Zlatanović, Milorad
Stefanović, Bogdan
One of the methods of resolving the transport problem in cutting, transfer and deposition of earth material during forest road construction was presented. The optimal plan of earth material distribution is achieved by minimising the total transport costs, solving the transport problem by linear programming. Now it is necessary to abandon the previously used method of graphical levelling of masses by the method of optimisation. The presented method is the optimal solution of earth material transport from the cut or borrow pit and its distribution into the fills or stockpiles, with simple application and with the software which supports the methodology.
U radu je predstavljen jedan od načina rešavanja transportnog problema pri iskopu, premeštanju i deponovanju zemljanog materijala u toku gradnji šumskih puteva. Izrada optimalnog plana rasporeda zemljanog materijala se postiže minimiziranjem ukupnih troškova transporta rešavanjem transportnog problema linearnog programiranja. Dobijanje optimalnog rešenja transporta zemljanog materijala iz useka ili pozajmišta i njihov raspored u odgovarajuće nasipe iii deponije, jednostavnost primene i postojanje softvera koji podržava predstavljanu metodologiju zahteva napuštanje do sada korišćenog metoda grafičkog nivelanja masa primenom metode optimizacije.
srpski
2002
© All rights reserved
forest roads, forest road construction, linear programming, transport problem, optimisation
šumski putevi, gradnja šumskih puteva, Iinearno programiranje, transportni problem, optimizacija